See growth work before it becomes a final-account dispute

ProjectVIEW ERP links the owner’s repair specification with estimates, work packages and actual costs. Record additional findings, review their estimated impacts and track owner approvals, so the yard and fleet manager can work from documented project information.

Ship Repair & Maintenance

See growth work before it becomes a final-account dispute

Managing Short-Notice, High-Intensity Repair Projects

A repair quotation starts with the owner’s specification, but opening-up inspections may reveal more work. Record each finding before it becomes an undocumented instruction. Then assess the proposed scope, price and expected completion impact with the owner.

ProjectVIEW ERP enables shipyards to capture costs and scope changes in real time, ensuring emerging work is visible, priced, and controlled from day one.

Example:
Record and track additional steel renewal or machinery repair works identified during inspection before they are executed without commercial approval.

Controlling Labor Productivity in Confined, Parallel Work Environments

Repair yards operate with multiple trades working simultaneously in confined spaces, often on a 24/7 basis. Labor productivity, overtime, and access constraints are major cost drivers.

ProjectVIEW ERP provides real-time visibility into labor deployment, productivity, and overtime costs by work package and vessel zone, enabling proactive management of labor-driven overruns.

Example:
Identify productivity losses caused by access conflicts between trades and re-sequence works to reduce overtime exposure.

Managing Material Availability and Urgent Procurement

Repair works often require urgent procurement of spare parts, consumables, and class-approved materials, frequently under premium pricing and expedited delivery.

ProjectVIEW ERP links procurement, inventory, and cost tracking to ensure urgent purchases remain visible and commercially controlled.

Example:
Track premium freight and expedited procurement costs separately to understand their impact on repair margins.

Controlling Variations and Commercial Exposure

Ship repair margins are highly sensitive to uncontrolled scope growth and unapproved variations. Without disciplined variation management, repair projects quickly become loss-making.

ProjectVIEW ERP provides structured variation tracking and financial impact assessment, ensuring additional works are identified, approved, and recoverable.

Example:
Assess the commercial impact of owner-requested additional maintenance works before committing yard resources.

Three Repair Modes, One Cost Baseline

Repair yards run three kinds of work, often on the same vessel at the same time:

  • Planned dry-docking. Budgeted from the owner’s repair specification, with dock days, blasting and painting, steel renewal and machinery overhaul priced item by item.
  • Expedient and voyage repairs. Unplanned work that needs a price and an approval within hours, at a premium cost.
  • Riding crew repairs. Work done at sea by a travelling team, with labor and materials charged to the vessel.

ProjectVIEW ERP puts all three under one vessel project with one BoQ ↔ WBS ↔ Cost Codes structure. Planned, expedient and riding-crew costs stay separate for control, but roll up into one margin per vessel.

Repair Estimating and Quotation from the Owner’s Specification

Enter or import each item of the owner’s repair specification as a BoQ item. Price it from the yard’s own rate library: steel per tonne, piping per metre, blasting and coating per m², crane hours, dock days, and labor norms per trade. Once the owner accepts the quotation, the same BoQ becomes the budget, with no re-keying. Growth work found later is priced against the same rates, so the owner sees consistent pricing.

Growth Work and Variations Under Control

Opening-up and inspection can reveal additional work. In ProjectVIEW ERP, each new finding is a variation linked to the original specification item. It has its own estimate and approval status, and its cost is tracked separately until the owner approves it. Unapproved work is visible every day, not discovered at final invoicing.

Dock and Berth Utilization

Plan dock and berth occupancy across all vessels in the yard. Track dock-day cost and overstay per vessel, and see early when a delayed vessel will block the next docking.

Owner, Class and Warranty Records

Store inspection reports, class surveyor findings, thickness measurements, photos and owner approvals against each BoQ item in the Common Data Environment. Final invoice reconciliation, owner disputes and warranty claims are then backed by records, not memory.

What Repair Yards Measure with ProjectVIEW

  • Margin per vessel, actual against quotation
  • Growth work as a percentage of the original contract
  • Labor hours per trade, actual against estimate
  • Dock days, planned against actual
  • Value of variations waiting for owner approval
  • Days from vessel redelivery to final invoice

Shipyard reference: DANAOS has experience supporting shipyard operations, including Papilas Shipyard.

Related reading: Ship Repair ERP: dry docking, expedient works and riding crew · Dry Docking Governance: a fleet manager’s view · Shipyard Management Software overview

FAQ

FAQ: Ship Repair Management Software

What is ship repair management software?

Software that controls a repair yard’s full commercial and operational cycle per vessel: specification-based estimating, quotation, work orders, labor, materials, subcontractors, variations and final invoicing. ProjectVIEW ERP does this on one BoQ ↔ WBS ↔ Cost Codes structure, so the quotation, the budget and the actual cost use the same breakdown.

Can ProjectVIEW quote directly from an owner’s repair specification?

Yes. Specification items become BoQ items priced from the yard’s rate library and labor norms. The accepted quotation becomes the project budget without re-entry.

How does ProjectVIEW handle growth work found after opening up?

Each finding is recorded as a variation linked to the original specification item, priced from the same rates and sent for owner approval. Its cost is tracked separately until approval, so unapproved work is visible before invoicing.

Does ProjectVIEW replace our accounting system?

It can. ProjectVIEW includes accounting, finance, and payables and receivables per project. It can also integrate with an existing corporate ERP such as SAP or Oracle through its API and native connectors.

How long does implementation take in a ship repair yard?

Implementation is scoped around data migration, integrations, deployment and agreed workflows. DANAOS engineers support delivery on Microsoft Azure or on-premises. A pilot-vessel approach and its acceptance criteria can be agreed as part of the implementation plan.