Marine construction and upstream projects do not start offshore. They start at the budget.
During budgeting, the Bill of Quantities (BoQ) and the Work Breakdown Structure (WBS) already define:
- What work will be executed (activity description – WBS)
- In what quantity and intensity (BoQ)
- Over what time window (rough-cut schedule)
From that point, the type and category of construction vessels and heavy marine equipment are no longer assumptions—they are budgeted project resources.
A piling activity implies a pile-driving vessel or jack-up. A trenching BoQ implies a CSD, backhoe dredger, or a substitute spread. A deepwater installation activity implies a DP construction vessel.
This is where ProjectVIEW ERP starts—before the project ever mobilizes.
From BoQ & WBS to Vessel Type and Replacement Logic
ProjectVIEW directly links:
- BoQ quantities → workload intensity
- WBS activities → execution method
- Execution method → vessel category and acceptable replacements
For each activity, ProjectVIEW defines:
- Primary vessel type
- Approved replacement vessels
- Operating mode (DP, anchored, spud, sailing)
- Expected productivity rate
- Associated crew and operators
This eliminates vague planning like:
“We’ll probably need a crane barge around that time.”
Instead, the system knows:
“This activity consumes 420 operating hours of a DP crane vessel or an approved anchored alternative.”
Budgeting Is Impossible Without Maintenance, HR, and Tools Alignment
This is where most systems collapse.
You cannot budget vessel availability without knowing:
- Maintenance windows
- Consumed operating hours
- Crew certification and rotations
- Tooling and spare readiness
ProjectVIEW forces budgeting to align with:
- Maintenance schedules linked to operating hours
- Tooling and auxiliary equipment availability
- Crew, operators, and certifications
- Spare parts criticality
The result is speculated but realistic availability, not optimistic fiction.
A vessel is not “available” if:
- It is 80 hours away from mandatory service
- The certified DP crew is not available
- Critical spares are not in stock
- A replacement vessel violates project constraints
ProjectVIEW blocks these conflicts at budget stage, not offshore.
Planning & Mobilization Through Resource Levelling
Once budgeted, ProjectVIEW moves to planning and mobilization, where everything is leveled against time and activity sequence:
- Vessels
- Replacement spreads
- Heavy machinery
- Operators and crew
- Tools and support equipment
Planning is not done in isolation.
ProjectVIEW schedules:
- Vessel availability vs WBS activities
- Crew rotations vs operating modes
- Maintenance windows vs critical path
- Replacements when primary assets are constrained
Mobilization is not a date—it is the result of resource levelling across time.
Project-Consumed Hours Drive Maintenance and Availability
Once execution starts, ProjectVIEW tracks actual project-consumed operating hours:
- Per vessel
- Per operating mode
- Per project
- Per activity
Maintenance is triggered by:
- Running hours
- Dredging hours
- Crane lifting hours
- DP hours
- Engine or auxiliary usage
Not calendar guesses.
When thresholds are reached:
- Maintenance is scheduled automatically
- Asset availability is blocked
- Spares and services are triggered
- Costs are charged to the project that consumed the hours
This creates project accountability, not fleet-level ambiguity.
Operator and Crew Matching Is Enforced, Not Assumed
A vessel without the right crew is a liability.
ProjectVIEW enforces:
- Operator–vessel compatibility
- Certification validity
- Experience per vessel class
- Fatigue, rotation, and compliance rules
Crew is planned with the vessel, not after it.
Why Only ProjectVIEW ERP Can Do This
Generic ERPs manage:
- Assets as static registers
- Maintenance as accounting events
- Crew as HR records
- Planning in disconnected tools
Marine construction does not work that way.
ProjectVIEW ERP is the only project-centric system that orchestrates:
- Vessels and heavy equipment
- Approved replacements
- Maintenance driven by project-consumed hours
- Operators and crew
- Tools and spares
- Budgeting, planning, mobilization, and execution
All within one project context, governed by BoQ, WBS, time, and cost.
Bottom Line
Marine construction is not about owning assets. It is about orchestrating constrained, expensive, high-risk resources against time.
ProjectVIEW ERP does not ask:
“Do we have a vessel?”
It asks:
“Can this project execute this activity, at this time, with this vessel, this crew, and this remaining maintenance life?”
That is the difference between planning and control.