What Is Claims Management?

Claims management is the discipline of pursuing and defending contractual entitlements when agreement cannot be reached through normal variation processes.

In capital projects, claims arise when parties disagree about scope, entitlement, valuation, or responsibility—and when contemporaneous records determine outcomes. The difference between a successful claim and a failed one is rarely the merits; it is the evidence. Projects that capture changes in real-time at the point of work, secure approvals through systematic workflows, and maintain auditable records protect their commercial position. Projects that rely on reconstruction from memory and scattered documents invite disputed outcomes and eroded margins.

Definition

Claims management is the systematic process of identifying, documenting, substantiating, submitting, negotiating, and resolving contractual claims arising from capital project execution.

A claim is a formal request for additional payment, time extension, or other relief under a contract, submitted when the claimant believes they are entitled to compensation beyond what has been agreed through normal variation processes.

In capital projects, claims management addresses several categories of disputed entitlement:

  • Variation claims: Disputed valuation of instructed changes
  • Extension of time claims: Requests for schedule relief due to delay events
  • Prolongation claims: Cost recovery for extended project duration
  • Disruption claims: Compensation for productivity loss caused by employer or third-party actions
  • Acceleration claims: Recovery of costs incurred to mitigate delays
  • Unforeseen conditions claims: Entitlement arising from physical conditions differing from contract assumptions
  • Change in law claims: Compensation for regulatory changes affecting project cost or duration
  • Termination claims: Entitlement arising from contract termination

 

Effective claims management requires:

  • Contemporaneous records: Documentation created at the time events occur, not reconstructed later
  • Real-time capture: Recording of events, instructions, and impacts as they happen on site or in the yard
  • Digital approval workflows: Systematic processes for obtaining and documenting stakeholder acknowledgment
  • Contractual compliance: Adherence to notice requirements, time limits, and procedural obligations
  • Causation analysis: Clear demonstration of cause-and-effect between events and claimed impact
  • Quantum substantiation: Detailed calculation of claimed amounts with supporting evidence
  • Professional presentation: Clear, well-organised claim documents that facilitate assessment

 

Claims management is distinct from variation management in that claims address disputed matters where normal agreement processes have not succeeded.

However, the foundation for successful claims is laid through effective variation and change management—particularly the real-time capture of events and systematic documentation that begins when changes first occur.

Stakeholder Risk Exposure

Claims management affects all project stakeholders, with exposure depending on contract type, project complexity, and the effectiveness of contemporaneous documentation systems.

Risk Exposure by Industry

Stakeholder Construction Marine & Offshore Shipbuilding Mining Project-Based Manufacturing
Client / Owner 6 7 5 8 5
Contractor / Builder 7 8 8 7 7
Consultant / Supervisor 4 5 4 5 4
Designers 5 6 6 5 6
Laboratories / QC 2 3 3 3 3
QA and HSE 4 6 5 7 4
Lenders / Banks 5 7 6 8 4
Insurers 5 7 6 7 5

Rating Scale: 1 = Lowest risk exposure, 10 = Highest risk exposure

Stakeholder Roles in Claims Management

Stakeholder Role in Claims Management Key Concerns
Owner / Developer / E&P Operator Receives and assesses claims; defends against unjustified claims; settles valid claims Cost exposure, project budget, dispute avoidance
Contractor / Shipbuilder / Mining Contractor Prepares and submits claims; substantiates entitlement; negotiates settlement Entitlement recovery, margin protection, cash flow
Consultant / Independent Engineer / Employer’s Representative Assesses claims on behalf of owner; certifies valid entitlements; provides expert opinion Fair assessment, professional liability, contractual compliance
Designer / Architect / Naval Architect Provides technical information; may be subject to claims for design errors Liability exposure, PI insurance, documentation
QA and HSE Provides records supporting or defending claims Documentation accuracy, compliance evidence
Lenders / Project Finance Banks Monitors claims exposure; assesses impact on project cost and viability Budget impact, completion risk, covenant compliance
Insurers / Sureties May provide coverage for certain claims; assesses claims impact on project risk Coverage determination, subrogation rights

The Critical Role of Real-Time Capture

The foundation of successful claims management is contemporaneous documentation—records created at the time events occur, not reconstructed weeks or months later. Modern project delivery demands real-time capture systems that operate at the point of work.

Why Contemporaneous Records Matter

Record Type Created in Real-Time Reconstructed Later
Credibility High—records created when events fresh Low—records questioned as self-serving
Accuracy High—details captured immediately Low—memory fades, details lost
Completeness High—systematic capture ensures coverage Low—gaps where events not recalled
Audit trail Clear—timestamps, locations, authors verified Unclear—authenticity questioned
Dispute outcome Favourable—evidence supports narrative Unfavourable—lack of evidence undermines position

The Cost of Poor Documentation

Claims fail not because they lack merit but because they lack evidence:

Documentation Failure Consequence
No contemporaneous notice Contractual time bar; claim rejected procedurally
No site records of event Cannot prove event occurred as described
No record of instruction Disputed whether instruction was given
No productivity records Cannot quantify disruption impact
No approval documentation Disputed whether work was authorised
Reconstructed records Credibility challenged; records discounted

Real-Time Capture at Point of Work

Effective claims management requires capturing information where work happens:

Site and yard capture requirements:

Information Type Capture Method Timing
Daily conditions Digital daily report with photos End of each shift
Instructions received Logged with date, time, source, content Immediately upon receipt
Events and incidents Incident report with witnesses, photos Within hours of occurrence
Resource deployment Labour, equipment, material records Daily
Progress achieved Quantity surveys, progress photos Daily or as work completes
Delays encountered Delay notice with cause and impact Same day
Changed conditions Condition report with documentation Upon discovery

Mobile and field capture technology:

Modern claims protection requires technology that enables capture at the point of work:

  • Mobile applications for site personnel to record events
  • Photo and video capture with automatic timestamps and geolocation
  • Voice-to-text for rapid narrative recording
  • Offline capability for remote sites without connectivity
  • Automatic synchronisation when connectivity restored
  • Integration with project control systems

Digital Approval Workflows and Portal-Based Documentation

The second critical element of claims protection is systematic approval workflows—obtaining and documenting stakeholder acknowledgment of events, instructions, and impacts through digital systems that create auditable records.

Why Portal-Based Approval Matters

Traditional paper-based or email-based approval processes create vulnerabilities:

Traditional Approach Vulnerability
Paper site instructions Lost, damaged, disputed authenticity
Email chains Buried in inboxes, incomplete threads, version confusion
Verbal instructions No record; disputed whether given
Manual sign-off Delayed, incomplete, disputed signatures
Scattered documentation Cannot locate records when needed

Digital portal-based systems address these vulnerabilities:

Portal Capability Claims Protection Benefit
Centralised repository All records in one searchable location
Automatic timestamps Indisputable record of when documents created/submitted
User authentication Clear identification of who created/approved records
Workflow enforcement Cannot bypass required approvals
Audit trail Complete history of all actions and changes
Version control Clear record of document evolution
Notification and escalation Ensures timely response to submissions
Access control Appropriate visibility for all stakeholders

Portal-Based Approval Workflow

Event Occurs on Site/Yard
           │
           ▼
┌─────────────────────────────┐
│ Site/Yard Personnel         │
│ Captures Event via Mobile   │
│ App with Photos/Details     │
│ (Timestamped, Geolocated)   │
└──────────────┬──────────────┘
               │
               ▼
┌─────────────────────────────┐
│ Automatic Upload to         │
│ Project Portal              │
│ (Even from Remote Sites)    │
└──────────────┬──────────────┘
               │
               ▼
┌─────────────────────────────┐
│ Contractor PM Reviews       │
│ and Submits Formal Notice   │
│ via Portal                  │
└──────────────┬──────────────┘
               │
               ▼
┌─────────────────────────────┐
│ Automatic Notification to   │
│ Client/Consultant via       │
│ Portal                      │
└──────────────┬──────────────┘
               │
               ▼
┌─────────────────────────────┐
│ Client/Consultant Reviews   │
│ in Portal with Full         │
│ Supporting Documentation    │
└──────────────┬──────────────┘
               │
         ┌─────┴─────┬──────────────┐
         │           │              │
      APPROVE    REQUEST INFO    REJECT
         │           │              │
         ▼           ▼              ▼
┌──────────────┐ ┌──────────┐ ┌──────────────┐
│ Approval     │ │ Query    │ │ Rejection    │
│ Recorded     │ │ Logged   │ │ Recorded     │
│ with         │ │ Response │ │ with         │
│ Timestamp    │ │ Required │ │ Reasons      │
│ and User ID  │ │          │ │ (Preserved   │
│              │ │          │ │ for Claim)   │
└──────────────┘ └──────────┘ └──────────────┘
         │                          │
         ▼                          ▼
┌─────────────────────────────────────────────┐
│ Complete Audit Trail Available for          │
│ Claims Substantiation or Defence            │
└─────────────────────────────────────────────┘

Stakeholder Portal Access

Different stakeholders require different portal access for claims-related documentation:

Stakeholder Portal Access Typical Actions
Contractor Site Team Event capture, daily reports, photo upload Record events as they occur
Contractor PM Review, submit notices, variation requests Formalise claims-relevant submissions
Contractor Commercial Claims preparation, quantum documentation Compile and substantiate claims
Client/Owner PM Review submissions, approve/reject/query Respond to contractor submissions
Consultant/Engineer Review, certify, provide determinations Assess and certify entitlements
Subcontractors Event capture, submit claims upstream Document sub-level events
Lenders (view only) Monitor claims status and exposure Assess project risk

Approval Documentation Requirements

For claims protection, portal approval workflows must capture:

Element Requirement Claims Value
Instruction acknowledgment Client/consultant confirms receipt of notice Proves notice was given
Event acknowledgment Client/consultant acknowledges event occurred Establishes factual basis
Impact acknowledgment Agreement on principle of impact (even if quantum disputed) Establishes causation
Direction to proceed Instruction to execute work despite dispute Protects entitlement
Rejection with reasons Documented basis for rejection Preserved for claim/dispute
Time-stamped responses When responses provided Proves compliance with time limits

Context in Project-Based Industries

Claims management operates across all project-based industries, with practices reflecting industry-specific contractual frameworks, typical disputes, and documentation requirements.

Construction

In construction, claims commonly arise from:

Claim Type Typical Causes Documentation Requirements
Extension of time Weather, late information, variations, third parties Delay analysis, programme updates, notices
Prolongation costs Extended site presence due to excusable delay Resource records, cost substantiation
Disruption Out-of-sequence work, acceleration, congestion Productivity records, measured mile analysis
Variations Disputed scope, valuation methodology, rates Instructions, measurements, cost build-ups
Unforeseen ground Differing site conditions from contract basis Site investigation, condition reports, expert opinion

Key characteristics:

  • Standard forms (FIDIC, NEC, JCT) have specific claims procedures
  • Time bars for notice are strictly enforced
  • Quantity surveyor role in claims assessment
  • Adjudication commonly used for interim resolution

Site capture priorities:

  • Daily diaries with weather, resources, progress, events
  • Photographic records of conditions and progress
  • Instruction logs with immediate capture
  • Delay notices submitted same-day via portal

 

Marine and Offshore

In marine and offshore projects, claims reflect high-value operations:

Claim Type Typical Causes Documentation Requirements
Vessel standby Weather delays, client readiness, access Vessel logs, weather records, standby notices
Weight growth Design development beyond tolerance Weight reports, design change records
Offshore delays Installation issues, hook-up complexity Daily offshore reports, progress records
Change orders Scope evolution, interface changes Change documentation, impact assessments

Key characteristics:

  • High daily rates magnify delay impacts
  • Weather records critical for delay claims
  • Multiple contractor interfaces create complexity
  • Lender scrutiny of claims exposure

 

Yard and offshore capture priorities:

  • Vessel daily reports with automatic upload
  • Weather station data integration
  • Weight tracking with variance alerts
  • Offshore progress with photo/video documentation

 

Shipbuilding

In shipbuilding, claims address long production cycles:

Claim Type Typical Causes Documentation Requirements
Owner changes Specification modifications Change request documentation, impact assessments
OFE delays Owner-furnished equipment late delivery Delivery schedules, delay notices, mitigation records
Classification changes Rule changes, surveyor requirements Classification correspondence, compliance costs
Currency claims Exchange rate movements (if contractual) Rate records, contract provisions

Key characteristics:

  • Long build cycles create change accumulation
  • Currency provisions vary by contract
  • Owner-furnished equipment creates interface claims
  • Milestone payment disputes common

 

Yard capture priorities:

  • Production records by block and zone
  • OFE delivery tracking with automatic alerts
  • Classification survey records
  • Change instruction logs with owner approval

 

Mining

In mining projects, claims reflect geological and remote execution challenges:

Claim Type Typical Causes Documentation Requirements
Geotechnical Ground conditions differing from baseline Geological records, condition reports, expert opinion
Scope changes Resource updates, process modifications Change documentation, cost impact
Regulatory Permit conditions, compliance requirements Regulatory correspondence, compliance costs
Remote site Logistics, weather, access constraints Site records, delay documentation

Key characteristics:

  • Geological uncertainty creates significant claims exposure
  • Multiple contractor interfaces in EPCM delivery
  • Remote sites challenge documentation systems
  • Community and regulatory claims increasing

 

Site capture priorities:

  • Geological logging with digital capture
  • Daily site reports even in remote conditions
  • Weather and access records
  • Regulatory correspondence tracking

Project-Based Manufacturing

In project-based manufacturing, claims address specification and delivery disputes:

Claim Type Typical Causes Documentation Requirements
Specification changes Client modifications, design development Change orders, impact assessments
Delivery delays Site not ready, sequence changes Delivery notices, storage costs
Inspection delays Client inspection not timely Inspection schedules, delay records
Rejection disputes Disputed non-conformance Inspection records, technical substantiation

Key characteristics:

  • BIM/design integration enables rapid change identification
  • Delivery coordination claims common
  • Quality documentation critical for rejection disputes
  • Clear specification baseline essential

 

Factory capture priorities:

  • Production records by element and project
  • Inspection and test documentation
  • Delivery scheduling with client confirmation
  • Change instruction capture with approval workflow

Why This Concept Exists

Claims management exists because capital projects involve complex contractual relationships where disagreements are inevitable and significant sums are at stake.

Contracts cannot anticipate every situation

Even well-drafted contracts cannot address every circumstance:

  • Events occur that were not contemplated
  • Contract language is subject to interpretation
  • Parties have different understandings of obligations
  • Changed circumstances alter the balance of the agreement

 

Claims provide the mechanism for resolving disputes within the contractual framework.

Variation processes have limits

Normal variation management assumes parties can agree:

  • On what constitutes a variation
  • On the appropriate valuation
  • On entitlement to time relief
  • On responsibility and liability

 

When agreement fails, claims provide the escalation path.

Financial stakes justify formal process

Capital project claims involve significant sums:

  • Prolongation claims may represent months of site costs
  • Disruption claims may represent substantial productivity loss
  • Delay damages may be measured in millions
  • Disputed variations may accumulate to major exposure

 

These stakes justify the investment in formal claims management.

Contemporaneous records are the only reliable evidence

When disputes arise months or years after events:

  • Memories fade and differ between parties
  • Documents may be lost or incomplete
  • Personnel may have left the project
  • Self-serving reconstruction is challenged

 

Contemporaneous records—created in real-time at the point of work—provide the only reliable evidence for claims resolution.

Digital systems create the required audit trail

Traditional documentation methods cannot provide the audit trail that claims require:

  • Paper records are lost, damaged, or disputed
  • Email chains are incomplete and scattered
  • Verbal communications leave no trace
  • Manual processes have gaps and delays

 

Digital portal systems create the complete, timestamped, authenticated records that claims substantiation demands.

How It Works Conceptually

Claims management operates through a lifecycle from identification through resolution, supported by real-time capture and digital approval workflows.

Claims Lifecycle

Potential Claim Event
         │
         ▼
┌────────────────────┐
│ REAL-TIME CAPTURE  │
│ Site/yard records  │
│ event with photos, │
│ details, witnesses │
└─────────┬──────────┘
          │
          ▼
┌────────────────────┐
│ NOTICE             │
│ Formal notice via  │
│ portal within      │
│ contract time      │
│ limits             │
└─────────┬──────────┘
          │
          ▼
┌────────────────────┐
│ PORTAL APPROVAL    │
│ WORKFLOW           │
│ Client/consultant  │
│ acknowledges or    │
│ responds           │
└─────────┬──────────┘
          │
          ▼
┌────────────────────┐
│ SUBSTANTIATION     │
│ Compile detailed   │
│ claim with full    │
│ supporting         │
│ evidence           │
└─────────┬──────────┘
          │
          ▼
┌────────────────────┐
│ SUBMISSION         │
│ Formal claim       │
│ submitted via      │
│ portal with all    │
│ documentation      │
└─────────┬──────────┘
          │
          ▼
┌────────────────────┐
│ ASSESSMENT         │
│ Claim reviewed     │
│ and determined     │
└─────────┬──────────┘
          │
    ┌─────┴─────┐
    │           │
 AGREED     DISPUTED
    │           │
    ▼           ▼
┌────────┐  ┌────────────┐
│SETTLE- │  │ DISPUTE    │
│MENT    │  │ RESOLUTION │
└────────┘  └────────────┘

Notice Requirements

Most contracts impose strict notice requirements:

Requirement Typical Provision Consequence of Non-Compliance
Initial notice Within 7–28 days of event Time bar—claim rejected
Particulars Within 28–84 days of event Claim limited to noticed amount
Final claim Within defined period after event Entitlement lost
Continuing events Regular updates required Ongoing entitlement lost

Portal-based notice compliance:

System Capability Compliance Benefit
Automatic event timestamping Proves when event occurred
Notice templates Ensures required content included
Deadline tracking Alerts before time limits expire
Submission confirmation Proves notice was submitted
Receipt acknowledgment Proves notice was received
Audit trail Complete record for disputes

Claims Substantiation

A well-substantiated claim contains:

Section Content Evidence Source
Executive summary Overview of claim and relief sought
Factual narrative Chronological description of events Site records, daily reports, correspondence
Contractual basis Contract provisions establishing entitlement Contract documents, specifications
Causation Link between events and claimed impact Programme analysis, expert opinion
Quantum Detailed calculation of claimed amount Cost records, resource data, invoices
Supporting documents Evidence supporting all assertions Portal-stored documentation

Evidence hierarchy for claims:

Evidence Type Weight Source
Contemporaneous records Highest Real-time capture at point of work
Portal-documented approvals High Digital workflow with timestamps
Correspondence Medium-High Emails, letters (preferably in portal)
Expert analysis Medium Delay analysis, quantum assessment
Witness statements Medium Statements from project personnel
Reconstructed records Low Documents created after the fact

Delay Claims and Programme Analysis

Delay claims require programme-based analysis:

Analysis Method Description Application
As-planned vs. as-built Compare planned schedule to actual Simple delay demonstration
Impacted as-planned Insert delay events into baseline Prospective entitlement assessment
Collapsed as-built Remove delays from as-built Retrospective analysis
Time impact analysis Contemporaneous impact at each event Industry-preferred method
Windows analysis Period-by-period delay assessment Complex multi-cause delays

Disruption Claims and Productivity Analysis

Disruption claims require productivity evidence:

Analysis Method Description Evidence Required
Measured mile Compare disrupted to undisrupted productivity Detailed productivity records by period
Earned value Compare earned to planned productivity Progress and resource records
Industry studies Apply published productivity factors Recognised study data
Total cost Claim all overrun as disruption (least preferred) Elimination of other causes

Claims Negotiation and Resolution

Claims resolution follows escalating steps:

Step Process Typical Outcome
Project level PM-to-PM negotiation Settlement of straightforward claims
Commercial level Commercial manager negotiation Settlement of moderate claims
Executive level Senior management negotiation Settlement of significant claims
Mediation Facilitated negotiation Non-binding resolution attempt
Adjudication Binding interim decision Rapid resolution (common in construction)
Arbitration Binding final decision Formal dispute resolution
Litigation Court proceedings Last resort

Risk Exposure by Contract Type

Claims exposure varies significantly by contract type:

Stakeholder Fixed-Price Design-Build EPC EPCM Cost-Plus PPP/BOT
Client / Owner 5 4 3 7 8 7
Contractor / Builder 8 8 9 5 4 7
Consultant / Supervisor 4 5 4 7 5 5
Designers 5 8 8 5 4 6
Laboratories / QC 2 3 3 3 2 3
QA and HSE 3 4 4 4 3 5
Lenders / Banks 5 6 6 7 5 8
Insurers 5 6 7 5 4 7

Rating Scale: 1 = Lowest claims exposure, 10 = Highest claims exposure

Key observations:

  • EPC and Fixed-Price create highest contractor claims exposure—scope disputes and valuation disagreements concentrate risk
  • EPCM and Cost-Plus shift claims risk toward owners—contractor claims are fewer but owner exposure to cost growth is higher
  • Design-Build and EPC create designer claims exposure through design responsibility
  • PPP/BOT creates complex claims dynamics across construction, operation, and concession terms
  • Lenders face claims exposure through project cost and completion impact

Why Generic Approaches Fail

Generic enterprise systems fail to support effective claims management because they lack the real-time capture capability, approval workflows, and documentation structures that claims require.

No real-time site/yard capture

Claims depend on contemporaneous records created at the point of work. Generic systems:

  • Have no mobile capture capability for site personnel
  • Cannot capture photos with automatic timestamps and geolocation
  • Lack offline capability for remote locations
  • Cannot integrate field data with project control systems

 

No portal-based approval workflow

Claims protection requires documented approvals through systematic workflows. Generic systems:

  • Have no project-specific portal capability
  • Cannot enforce approval workflows for instructions and notices
  • Lack audit trails for stakeholder responses
  • Cannot track notice compliance and time limits

 

No integration with project control

Claims substantiation requires data from across project systems. Generic systems:

  • Cannot link claims to affected WBS and cost codes
  • Cannot extract resource and productivity data for quantum
  • Cannot integrate with schedule for delay analysis
  • Cannot connect variation registers with claims registers

 

No claims register capability

Claims management requires structured tracking:

  • Claim status and progression
  • Notice compliance monitoring
  • Settlement tracking
  • Dispute status

 

Generic systems lack claims-specific data structures and workflows.

Spreadsheet and email-based documentation creates fatal gaps

Many organisations manage claims documentation through spreadsheets and email:

  • No single source of truth
  • Version control problems
  • Incomplete audit trails
  • Documents scattered across inboxes
  • Cannot demonstrate contemporaneous capture
  • Vulnerable to challenge in disputes

Where it Applies

  • Project Execution. Ongoing identification and documentation of potential claims throughout construction.
  • Commercial Management. Claims preparation, submission, and negotiation as part of commercial function.
  • Variation Management. Escalation of disputed variations to formal claims.
  • Final Account. Claims resolution as part of project closeout and final account settlement.
  • Dispute Resolution. Claims documentation supporting adjudication, arbitration, or litigation.
  • Lessons Learned. Claims analysis for contract improvement and risk allocation refinement.

Common Misconceptions

Misconception: Claims are adversarial and should be avoided.

Reality: Claims are a legitimate contractual mechanism for resolving disputes about entitlement. Avoiding justified claims means accepting losses that the contract does not require. Professional claims management protects commercial position without unnecessary conflict.

Misconception: Good relationships eliminate the need for claims documentation.

Reality: Relationships change, personnel leave, and memories differ. Good relationships should make claims resolution easier, not claims documentation unnecessary. Contemporaneous records protect both parties regardless of relationship quality.

Misconception: Claims can be prepared after the project from available records.

Reality: Claims prepared after the fact from incomplete records are vulnerable to challenge. The credibility and completeness of contemporaneous documentation—created in real-time through systematic capture—determines claims outcomes.

Misconception: Notice requirements are formalities that can be addressed later.

Reality: Notice requirements are strictly enforced by tribunals and courts. Time-barred claims are rejected regardless of merit. Portal-based systems with automatic tracking prevent notice compliance failures.

Misconception: Small potential claims are not worth documenting.

Reality: Small claims accumulate; today’s minor issue may be part of tomorrow’s major claim. Systematic capture of all events through real-time systems costs little and protects against cumulative exposure.

Misconception: Digital systems are not accepted as evidence.

Reality: Properly implemented digital systems with audit trails, timestamps, and authentication are increasingly preferred over paper records. The key is demonstrating system integrity and contemporaneous capture.

Related Topics

  1. What Is Risk Management in Capital Projects? — Claims often arise from risk events; risk management informs claims exposure.
  2. What Is Change and Variation Management? — Disputed variations escalate to claims; change documentation supports claims.
  3. What Is a Risk Register? — Claims exposure should be tracked as project risk.
  4. What Is Contingency Management? — Claims affect contingency through both exposure and recovery.
  5. What Is Contractual Risk Allocation? — Contract terms determine claims entitlement.
  6. What Is Project Cost Control? — Claims values must integrate with cost management.